The consumer proving ground that ships first and proves the one personality backbone, before the premium B2B brand AAVATAI launches clean on top. This is the full work plan: phases, dated timeline, task-by-task breakdown, owners, effort and the honest time to a first dollar.
The product moved from eight Big-Five archetypes to six HEXACO signature types. The eight-archetype, 9-dollar version is superseded. The design move: measure on dimensions, narrate with named types, render as a unique configuration.
Measure honestly on HEXACO (the validated six-factor model, public-domain IPIP items), narrate with six named types, always show the real scores. Six is not arbitrary: each type is the one factor a person stands out on most, plus a secondary "shade" for 30 combinations without 30 boxes.
Names recommended, not locked; the factor mapping is fixed, the names are swappable and need trademark clearance. "Radiant" is flagged for a second look (close to beauty and skincare language). Vera maps to the Emotionality or Agreeableness type, to reconcile at sign-off.
A warm quiz that reflects the highest version of you back, where Co-Star trolls you.
Measure honestly on HEXACO, narrate with six named types, then show the full configuration across six lenses, so nobody gets boxed and everybody gets a portrait. The avatars are the salesforce, not the product. The customer buys a ladder of multi-lens reports plus a portable self-file that makes their own AI know them.
The validated measured backbone is five frameworks (HEXACO, Attachment/ECR, BIS/BAS, SDT, Schwartz), per Zara's Theory Measurement Overview and the Strand Signature brief. Thinking modes, strengths and the story layer are derived or reflective report content, not separately scored instruments.
Order bump +9 to 12 dollars (about 30 percent take). A 60 to 365 day guarantee. Teams kit about 397 dollars, hard no-hiring exclusion. No standalone consumer subscription at launch; the hosted AAVATme companion (12 to 19 dollars a month) comes later.
Nicola and Claude can build the whole funnel in roughly 3 to 4 weeks, and the build starts the moment the three founders agree the full concept. The launch date is not set by build time, and not by any one person's capacity. It is set by one thing:
The fix is simply to get the full concept agreed at the next sync; then the build proceeds straight away. With agreement reached promptly, the realistic earliest honest soft launch is early-to-mid August 2026, with the proof event running mid-August to end September, which fits the hard anchor of AAVATAI launching at end September. The trademark filing and the co-venture MOU run alongside and must clear before any public claim and the first sale, not before the build.
Owners: NIC Nicola CC Claude Code (also our legal research + drafting) ZAR Zara AZ Aziza. Estimates are working effort, not elapsed time. Status: done to do gated later.
| Task | Owner | Effort | Status |
|---|---|---|---|
| A1. Psychology sign-off: the six-HEXACO model, the six lenses, the De Bono-free thinking lens, the tone | NIC | 3-5 days | gate |
| A2. Lock the six type names (pick Option A or B) and the epithets | NIC | 1 day | gate |
| A3. Assemble the pilot instrument from public-domain IPIP (30-item doorway + ~100-120 full) | CC NIC | 2-3 days | to do |
| A4. Recruit 50-150 pilot respondents from the HF audience and network | NIC AZ | 3-5 days | to do |
| A5. Run the pilot including the two-week retest window (the long pole) | NIC | 2-3 wks elapsed | to do |
| A6. Analyse: internal consistency (alpha ≥0.70/factor), retest (r ≥0.70), lead-type stability, felt accuracy + willingness-to-pay vs the single-type report | CC NIC | 2-3 days | to do |
| A7. AI-disclosure + "for self-understanding, not diagnosis or hiring" standing language | CC NIC | 1 day | to do |
| Task | Owner | Effort | Status |
|---|---|---|---|
| B1. Trademark clearance + filing: the name + the chosen six type names + the lens and mode names, across US, UK/EU, AU | CC NIC | 2-4 days | gate |
| B2. Strip De Bono / Six Thinking Hats / the coloured-hats visual; confirm our own mode names everywhere | CC | 1 day | to do |
| B3. Confirm the exact public-domain IPIP HEXACO item set | NIC CC | 2-3 days | to do |
| B4. The co-venture MOU: three-way split, IP licensed not assigned, cost recovery, decisions, exit (Claude drafts, the three agree and sign) | CC NIC | 1-2 days | gate |
| B5. Consent copy, deletion on request, the AAVATtype-to-AAVATAI data wall, GDPR/UK/AU; claims wording drafted | CC | 2-3 days | to do |
| Task | Owner | Effort | Status |
|---|---|---|---|
| C1. Six-HEXACO scoring engine: percentile bands vs IPIP norms, headline type + shade, the balanced-navigator edge case | CC | 3-4 days | to do |
| C2. The 30-item IPIP doorway quiz (5/factor, reverse-keyed) wired to the engine | CC | 2-3 days | to do |
| C3. The profile genome schema (scores + bands, lens scores, type + shade, consent block, versioned, dataset-ready) | CC | 2-3 days | to do |
| C4. Free result page: type + shade + six factor bars + shareable signature card + the next step | CC | 3-4 days | to do |
| C5. The Living Signature renderer (Layer 0 core free; Layers 1-4 paid), deterministic and generative | CC | 1-2 wks | to do |
| C6. The full instrument (~100-120 items: 60 IPIP trait spine + values/SDT/reg-focus + thinking + connection + story) | CC | 4-5 days | gated by A1 |
| C7. Your Full Pattern report (HTML to PDF, six lenses, measured/interpreted labels, confidence bands) | CC | ~1 wk | gated by A1 |
| C8. AAVATme Mode 1 self-file generator (profile to "About Me" manual + paste-in custom-instructions block) | CC | 3-4 days | to do |
| C9. Three-tier checkout (19/29/49) + order bump + guarantee; Stripe wiring | CC | 3-4 days | needs Stripe |
| C10. Email infrastructure: Resend (transactional) + Brevo (broadcast), type-tagged; rewrite the day-sequence for six types | CC | 3-4 days | needs accts |
| C11. Re-map the Teams Kit from eight patterns to six types (team lens, friction/power pairs, blind spots) | CC | 3-4 days | to do |
| C12. Re-map the books (EPUB + journals) and the marketing content to six types | CC | 3-5 days | to do |
| C13. Analytics dashboard: quiz starts, opt-in %, per-type split, conversion, bump take, share rate, revenue | CC | 2-3 days | to do |
| C14. End-to-end QA as every type; scoring, tagging, delivery, payment, email and the data wall all fire | CC +crew | 2-3 days | to do |
| C0. Set up Stripe + Resend + Brevo accounts (unblocks C9 and C10) | NIC | 1 day | gate |
| Task | Owner | Effort | Status |
|---|---|---|---|
| D1. Casting brief for the lead type-avatar (Vera, the Emotionality or Agreeableness type) | CC | 1 day | to do |
| D2. Build the lead avatar in ComfyUI (generate set + LoRA-lock), then share the ComfyUI config so Nicola can emulate it | ZAR builds, NIC replicates | 3-5 days | to do |
| D2b. Stand up Nicola's local avatar generation to match Zara's config; free models on her MacBook M5 + SSD (zero-cost avatar assets) | NIC | 1-2 days | to do |
| D2c. Compare Draw Things vs the ComfyUI setup for Nicola's local generation and pick the tool (Draw Things stays a live option, just not yet evaluated against ComfyUI) | NIC ZAR | 1 day | to do |
| D3. Hero + about 12 scene stills | ZAR NIC | 3-5 days | to do |
| D4. The first video batch from the stills | ZAR (ComfyUI) | ~1 wk | to do |
| D5. Card art for the other five types (placeholder until their LoRAs) | CC ZAR | 2-3 days | to do |
| D6. The coded-signature to avatar-DNA translation (first pass) | CC ZAR | ~1 wk | later |
| D7. Document the AAVATAI Signature Build playbook + the AI-disclosure overlay standard | CC | 1 day | to do |
| Task | Owner | Effort | Status |
|---|---|---|---|
| E1. Re-skin the 90-day content calendar to six types + the new ladder | CC | 1-2 days | to do |
| E2. The auto signature share-card generator ("I'm Radiant. What avatar are you?") | CC | 2-3 days | to do |
| E3. The no-gate "Pattern in Crisis" micro-quiz | CC | 2 days | to do |
| E4. Grab @aavattype and @aavattwin on IG, TikTok, X, YouTube | NIC +crew | 1 day | to do |
| E5. 301-redirect the typo domains; confirm auto-renew on all four | CC NIC | 0.5 day | to do |
| E6. Pinterest: six signature-card pins + a "which avatar are you" board | AZ | 1-2 days | to do |
| E7. Batch-produce the launch content (reels, carousels) while the team is together | AZ ZAR | ongoing | to do |
| E8. Add @brain.nourishmentt as a hooklab research account; voice-pass every caption before posting | CC NIC | ongoing | to do |
| Task | Owner | Effort | Status |
|---|---|---|---|
| F1. Re-map the Teams kit to six types (see C11) | CC | see C11 | to do |
| F2. The Stripe or invoice link for $397 / $497 | NIC | 0.5 day | to do |
| F3. Name three warm caring-sector contacts; pick the Tier 1 first conversation | NIC | 1 day | to do |
| F4. Send the approved outreach to the first org (post sign-off) | crew | ongoing | post sign-off |
| F5. Deliver the first Teams session (using /team/guide) | crew | 90 min | proof event |
| Task | Owner | Effort | Status |
|---|---|---|---|
| G1. The private beta cohort + the testimonial-capture flow | crew CC | ~2 wks | to do |
| G2. The AAVATAI pre-launch page live before "powered by AAVATAI" appears anywhere | CC NIC | 2-3 days | to do |
| G3. Soft launch the minimum sellable funnel | all | milestone | on sign-off |
| G4. Watch the gates: 40%+ opt-in, conversion, bump take, per-type split | all | ongoing | proof event |
The build work (Workstream C plus the writing in A, B, E) totals roughly 6 to 8 focused weeks of effort, but it parallelises and most of it is not gated. The funnel is buildable in 3 to 4 weeks of wall-clock, and Nicola can start the moment the concept is agreed.
She can move on the sign-off, the build, the accounts and her own avatar setup immediately. The real constraint is three-way agreement between Nicola, Aziza and Zara on the full concept, and right now the team can only meet on weekends, so concept decisions move at the pace of the weekend syncs. Lock the concept at the next sync and the build proceeds straight away.
The one unavoidable elapsed-time item is the two-week retest pilot on the science side. It cannot be compressed, so kick it off as soon as the instrument is agreed. Earliest honest soft launch: early-to-mid August 2026. Proof event to end September. The team-in-Australia window (to 31 December) is the hard deadline for all avatar production.